MTR has announced the phased opening of Tuen Ma Line

- Hong Kong, China
MTR has announced the phased opening of Tuen Ma Line

After completing a detailed feasibility study, it has been accepted that the phased opening of the Tuen Ma Line is feasible with a view of opening in the first quarter of 2020

The Corporation has also submitted the report to Government on the holistic assessment study for Hung Hom Station Extension, and the report on the verification study on as-constructed conditions of the North Approach Tunnels (NAT), South Approach Tunnels (SAT) and Hung Hom Stabling Sidings (HHS), all being parts of the Shatin to Central Link (SCL) project.

Jacob Kam, Chief Executive Officer of MTR Corporation, said: “There has been much public concern over the construction issues relating to the SCL, which have delayed the opening of this project so eagerly awaited by the local communities. Under the proposed arrangements, three new stations along the Tuen Ma Line (TML) are planned to open for passenger service in the first quarter of 2020 while continued efforts will be made to complete the rest of the TML as soon as possible.”

The Corporation is now undertaking necessary system modifications works, including adjustment of the signalling system, some re-cabling works, and modifications to some of the signage, which will allow the opening of the first phase of TML covering Hin Keng, Diamond Hill and Kai Tak stations, once all statutory processes have been completed. Upon opening of this first phase of the TML, passengers travelling on the Ma On Shan Line will be able to travel directly to Kai Tak Station in East Kowloon district via Hin Keng Station and Diamond Hill Station.

Roger Bayliss, Projects Director of MTR Corporation, commented: “Safety and quality of railway projects are of top priority to the MTR Corporation. We have completed a detailed verification of the Hung Hom Station Extension and related works based on methodologies agreed with Government. Given we have agreed the conclusions of the two reports with Government we will now proceed with the implementation of the suitable measures. I believe this is a pragmatic way to take forward the project and restore public confidence in our railway projects.”

Details of the suitable measures at the platform slabs and tunnel structures under the Hung Hom Station Extension as well as HHS are subjected to detailed design and acceptance from Government, which is expected to take four to six months to complete. Subsequent to obtaining the necessary acceptance from Government, the suitable measures are expected to take nine to 12 months to complete on site.

About Intelligent Transport

Intelligent Transport LogoServing the transport industry for more than 15 years, Intelligent Transport (formerly Eurotransport) is the leading source for information in the urban public transport sector. Covering all the new technologies and developments within this vitally important sector, Intelligent Transport provides high-quality analysis across our core topics: Smart Cities, Digitalisation, Intermodality, Ticketing and Payments, Safety and Security, The Passenger, The Fleet, Business Models and Regulation and Legislation. With articles from across the globe, we explore how and why industry decision makers operate the way they do, and examine how technology is changing the dynamics of transport.

  • Join our community for FREE today!

  • Create and share your own profile

  • Join the discussions

  • Publish your own items

  • Subscription to our Weekly eNewsletter

your benefits?

Get connected with Mass Transit Professionals Worldwide

Create your account

Go To Registration

FREE membership benefits

  • * create and share your own profile
  • * join the discussions
  • * publish your own items on Mass Transit Networkmanage news, jobs, tenders, companies, events, showcases, educations, associations and literature.
  • * subscribe to our eNewsletter
Add news yourself

Comments

There are no comments yet for this item

Join the discussion

You can only add a comment when you are logged in. Click here to login